Dear customers, welcome to browse our products. As the society developing and technology advancing, we live in an increasingly changed world, which have a great effect on the world we live. In turn, we should seize the opportunity and be capable enough to hold the chance to improve your ability even better. We offer you our 70-177 test braindumps: TS: Microsoft Project Server 2010, Configuring here for you reference. So let us take an unequivocal look of the 70-177 exam cram as follows
High quality questions
There are nothing irrelevant contents in the 70-177 exam braindumps: TS: Microsoft Project Server 2010, Configuring, but all high quality questions you may encounter in your real exam. Many exam candidates are afraid of squandering time and large amount of money on useless questions, but it is unnecessary to worry about ours. You will not squander time or money once you bought our 70-177 certification training. If you are uncertain about it, there are free demos preparing for you freely as a reference. With the high quality features and accurate contents in reasonable prices, anyone can afford such a desirable product of our company. So it is our mutual goal to fulfil your dreams of passing the Microsoft TS: Microsoft Project Server 2010, Configuring actual test and getting the certificate successfully.
Renew contents for free
After your purchase of our 70-177 training materials: TS: Microsoft Project Server 2010, Configuring, you can get a service of updating the materials when it has new contents. There are some services we provide for you. Our experts will revise the contents of our 70-177 exam preparatory. We will never permit any mistakes existing in our TS: Microsoft Project Server 2010, Configuring actual lab questions, so you can totally trust us and our products with confidence. We will send you an e-mail which contains the newest version when 70-177 training materials: TS: Microsoft Project Server 2010, Configuring have new contents lasting for one year, so hope you can have a good experience with our products.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Considerate service
We always adhere to the customer is God and we want to establish a long-term relation of cooperation with customers, which are embodied in the considerate service we provided. We provide services include: pre-sale consulting and after-sales service. Firstly, if you have any questions about purchasing process of the 70-177 training materials: TS: Microsoft Project Server 2010, Configuring, and you could contact our online support staffs. Furthermore, we will do our best to provide best products with reasonable price and frequent discounts. Secondly, we always think of our customers. After your purchase the materials, we will provide technology support if you are under the circumstance that you don't know how to use the 70-177 exam preparatory or have any questions about them.
The newest updates
Our questions are never the stereotypes, but always being developed and improving according to the trend. After scrutinizing and checking the new questions and points of Microsoft 70-177 exam, our experts add them into the 70-177 test braindumps: TS: Microsoft Project Server 2010, Configuring instantly and avoid the missing of important information for you, then we send supplement to you freely for one years after you bought our 70-177 exam cram, which will boost your confidence and refrain from worrying about missing the newest test items.
Microsoft TS: Microsoft Project Server 2010, Configuring Sample Questions:
1. You have a Project Server 2010 environment. You need to configure Project Server to allow members of the maintenance crew to choose their work assignments from a shared list. What should you do?
A) Create a Team Assignment Pool resource with Maintenance as the team name. Assign all crew members to the team.
B) Create a lookup table with the maintenance crew members' names. Link the lookup table to the Team Name built-in custom field. Create a Team Assignment Pool resource.
C) Select the Team Assignment Pool check box for each maintenance crew member.
D) Create a new SharePoint list of maintenance crew members. Assign read-only permissions to crew members. Import the SharePoint list to Project Server.
2. You have a Project Server 2010 environment. Project Site permissions are set to synchronize automatically. You need to grant a resource on a project team read/write access to the documents on the Project Site. What should you do before publishing the project?
A) Add the resource to the resource plan for the project.
B) Add the resource to the My Direct Reports category.
C) Add the resource to the Resource Managers group.
D) Assign the resource to a task in the project.
3. You have a Project Server 2010 environment. A project manager has accidently deleted 100 tasks from a project plan using Project Professional, and then saved and published the changes.
You need to restore the deleted tasks. What should you do?
A) Use Project Professional to open the project plan from the Published database and publish it.
B) Perform an Administrative Restore of the project from Project Web App (PWA).
C) Use Project Professional to open the project plan from the Active Cache and publish it.
D) Restore the Archive database in Microsoft SQL Server.
4. You have a Project Server 2010 environment. You create a custom view to display a list of delayed projects. You need to make sure that only senior managers in your company have access to the custom view. What should you do?
A) Create a new security template named Senior Managers.
B) Create a new group named Senior Managers.
C) Create a new category named Senior Managers.
D) Create a new user named Senior Managers.
5. You have a Project Server 2010 environment. Your company's CIO is performing an audit of the inactive tasks that project managers have in their project plans. However, the CIO cannot access inactive tasks in any Data Analysis view. You need to ensure that the company executives can access inactive tasks in the OLAP cube. What should you do?
A) Select the (Select All) check box for Built-in Measures in the Database Configuration page for the cube.
B) Include the Flag Status_Task field as a dimension in the cube.
C) Select the Include Inactive Tasks check box in the Database Configuration page for the cube.
D) Create a custom OLAP cube with a custom field named Inactive.
Solutions:
Question # 1 Answer: A | Question # 2 Answer: D | Question # 3 Answer: B | Question # 4 Answer: C | Question # 5 Answer: C |